Loan No.2289-PAK: Power Transmission Enhancement Investment Program
AWARD OF Contracts against Tender No.ADB-43-2008
LOT-I
For 220 kV Double Circuit
Twin Bundle T/Line From Dherki CCPP to Engro CCPP
to 220kV Rohri New Grid Station
Sr.No. |
Name
of Bidder
who submitted the bid
|
Quoted
Bid Price
Pak.Rs.
|
Corrected
Bid Price
Pak
Rs.
|
Discounted/
Corrected Bid Price
Pak Rs.
|
Evaluated
Bid Price
Pak
Rs.
|
Reasons
for Rejection if any |
Winning
Bidder Price
Pak Rs.
|
| 1 |
M/s. Nazir
& Company (Pvt.) Ltd., Lahore, Pakistan |
414,831,996 |
415,356,006 |
402,895,326
(3% Discount)
|
402,895,326 |
See Note #
1 |
|
| 2 |
M/s. NPI Construction
& Engineering, Karachi – Shams Construction Company, Quetta,
Pakistan (JV) |
382,496,507 |
421,645,964 |
421,645,964 |
421,645,964 |
See Note #
2 |
|
| 3 |
M/s. ICC (Pvt.)
Ltd., Lahore, Pakistan |
541,441,512 |
541,441,512 |
541,441,512 |
541,441,512 |
See Note #
3 |
541,441,512
See Note # 5 |
| 4 |
M/s. Potential
Engineers (Pvt.) Ltd., Lahore, Pakistan |
565,553,218 |
565,553,218 |
565,553,218 |
565,553,218 |
See Note #
4 |
|
NOTES
| 1 |
Due
to deficient validity of bid security, defective authority letter,
lack of equipment and incomplete financial documents. |
| 2 |
Due to defective
bid security and lack of experience, key personnel, equipment and
inadequate financial capability. |
| 3 |
Due to longer
completion time and incomplete offer. |
| 4 |
Due to shortfall
in the average annual turn over. |
| 5 |
Since none
of the bidder was responsive for this lot, therefore, due to urgency
of interconnection and to avoid heavy penalties M/s. ICC (Pvt.)
Ltd. having better position was recommended subject to withdrawal
of the deviations. |
LOT-II
For 220 kV Double Circuit
Twin Bundle T/Line From 220kV Rohri New Grid Station
to 220kV Shikarpur Grid Station
Sr.No. |
Name
of Bidder
who submitted the bid
|
Quoted
Bid Price
Pak.Rs.
|
Corrected
Bid Price
Pak
Rs.
|
Discounted/
Corrected Bid Price
Pak Rs.
|
Evaluated
Bid Price
Pak
Rs.
|
Reasons
for Rejection if any |
Winning
Bidder Price
Pak Rs.
|
| 1 |
M/s. NPI Construction
& Engineering, Karachi – Shams Construction Company, Quetta,
Pakistan (JV) |
394,039,898 |
395,959,848 |
395,959,848 |
395,959,848 |
See Note #
1 |
|
| 2 |
M/s. ICC (Pvt.)
Ltd., Lahore, Pakistan |
448,924,505 |
448,924,505 |
448,924,505 |
448,924,505 |
See Note #
2 |
|
| 3 |
M/s. Potential
Engineers (Pvt.) Ltd., Lahore, Pakistan |
514,439,915 |
514,439,915 |
514,439,915 |
514,439,915 |
|
514,439,915 |
| 4 |
M/s. M.R. Electric
– Al-Abdullah, Lahore, Pakistan (JV) |
628,348,392 |
572,171,949 |
514,954,754
(10% Discount)
|
514,954,754 |
See Note #
4 |
|
NOTES
| 1 |
Due
to defective bid security and lack of experience, key personnel,
equipment and inadequate financial capability. |
| 2 |
Due to longer
completion time and incomplete offer. |
| 3 |
Due to defective
and deficient bid securities and lack of requisite stringing equipment. |
LOT-III
| i) |
For 132kV Double Circuit T/Line from 220kV
Rohri New Grid Station to 132kV Gumbat Grid Station. |
| ii) |
For 132kV Double Circuit T/Line for In & Out of Two Circuits
of Rohri - Khairpur/Gumbat T/Line at Rohri New Grid Station.
|
Sr.No. |
Name
of Bidder
who submitted the bid
|
Quoted
Bid Price
Pak.Rs.
|
Corrected
Bid Price
Pak
Rs.
|
Discounted/
Corrected Bid Price
Pak Rs.
|
Evaluated
Bid Price
Pak
Rs.
|
Reasons
for Rejection if any |
Winning
Bidder Price
Pak Rs.
|
| 1 |
M/s. M.R. Electric
– Al-Abdullah, Lahore, Pakistan (JV) |
173,074,555 |
173,074,555 |
133,267,407
(23% Discount)
|
133,267,407 |
See Note #
1 |
|
| 2 |
M/s. NPI Construction
& Engineering, Karachi – Shams Construction Company, Quetta,
Pakistan (JV) |
146,950,083 |
146,724,944 |
146,724,944 |
146,724,944 |
See Note #
2 |
|
| 3 |
M/s. M. Yaqoob
& Sons – Sami Construction Co., Quetta, Pakistan (JV) |
152,992,005 |
149,395,725
|
149,395,725 |
149,395,725 |
See Note #
3 |
|
| 4 |
M/s. Usman
& Company and M.R. Construction Company, Sukkur, Pakistan (JV) |
162,271,300 |
162,271,300 |
162,271,300 |
162,271,300 |
See Note #
4 |
|
| 5 |
M/s. NEIE –
Al-Hussain Traders, Lahore, Pakistan (JV) |
198,963,192 |
198,963,192 |
198,963,192 |
198,963,192 |
|
198,963,192 |
| 6 |
M/s. Haji Nasib
Khan & Co. (Pvt.) Ltd, Quetta, Pakistan |
198,835,560 |
200,560,560 |
200,560,560 |
200,560,560 |
See Note #
5 |
|
| 7 |
M/s. Potential
Engineers (Pvt.) Ltd., Lahore, Pakistan |
230,019,800 |
230,019,770 |
230,019,770 |
230,019,770 |
|
|
NOTES
| 1 |
Due
to defective and deficient bid securities and lack of requisite
stringing equipment. |
| 2 |
Due to defective
bid security and lack of experience, key personnel, equipment and
inadequate financial capability. |
| 3 |
Due to defective
bid securities and lack of experience, key personnel, equipment
and incomplete financial documents. |
| 4 |
Due to lack
of experience, equipment and incomplete financial documents. |
| 5 |
Due to lack
of experience, key personnel, equipment and incomplete financial
documents. |
LOT-IV
For 132kV Double Circuit
T/Line from Jarwar CCPP to 132kV
Sadiqabad Grid Station
Sr.No. |
Name
of Bidder
who submitted the bid
|
Quoted
Bid Price
Pak.Rs.
|
Corrected
Bid Price
Pak
Rs.
|
Discounted/
Corrected Bid Price
Pak Rs.
|
Evaluated
Bid Price
Pak
Rs.
|
Reasons
for Rejection if any |
Winning
Bidder Price
Pak Rs.
|
| 1 |
M/s. M.R. Electric
– Al-Abdullah, Lahore, Pakistan (JV) |
174,072,368 |
174,072,368 |
134,035,723
(23% Discount)
|
134,035,723 |
See Note #
1 |
|
| 2 |
M/s. NPI Construction
& Engineering, Karachi – Shams Construction Company, Quetta,
Pakistan (JV) |
152,832,956 |
152,824,813 |
152,824,813 |
152,824,813 |
See Note #
2 |
|
| 3 |
M/s. NEIE –
Al-Hussain Traders, Lahore, Pakistan (JV) |
176,529,030 |
176,529,030 |
176,529,030 |
176,529,030 |
|
176,529,030 |
| 4 |
M/s. Haji Nasib
Khan & Co. (Pvt.) Ltd, Quetta, Pakistan |
199,907,100 |
199,907,100 |
199,907,100 |
199,907,100 |
See Note #
3 |
|
| 5 |
M/s. ICC (Pvt.)
Ltd., Lahore, Pakistan |
217,785,629 |
217,785,629 |
217,785,629 |
217,785,629 |
See Note # 4
|
|
| 6 |
M/s. Potential
Engineers (Pvt.) Ltd., Lahore, Pakistan |
227,918,762 |
227,918,762 |
227,918,762 |
227,918,762 |
See Note #
4 |
|
NOTES
| 1 |
Due to defective and deficient bid securities and
lack of requisite stringing equipment. |
| 2 |
Due to defective bid security and lack of experience, key personnel,
equipment and inadequate financial capability. |
| 3 |
Due to lack of experience, key personnel, equipment and incomplete
financial documents. |
| 4 |
Due to longer completion time and incomplete offer. |
|